Here's my third attempt at the CDS vignette - see anything amiss?

I'm unsure about drawing the footings - are they supposed to go to the top of the slab or the bottom? Does it matter?
You do not have the required permissions to view the files attached to this post.
te_mcg
 
Posts: 3
Joined: Sat May 23, 2015 3:43 pm

Re: CDS Vignette Attempt -

Postby Adadadad » Mon May 25, 2015 7:16 pm

Supposedly either top or bottom of slab, according to ncarb g+
https://plus.google.com/117247743507650 ... iuisZ4U525
But everyone here seems to do bottom of slab on grade. Literally, slab on grade


can't immediately verify the joist/duct height combos... but looks alright.
graphically speaking, take a look at some of my notes:
viewtopic.php?f=10&t=30016

Have you switched the cad file to do the 3.1 vignette yet?
User avatar
Adadadad
 
Posts: 23
Joined: Sun Feb 08, 2015 9:06 pm

Re: CDS Vignette Attempt -

Postby te_mcg » Thu May 28, 2015 7:59 pm

I did try the 3.1 vignette - attached. I think I have the duct clearance wrong in the Meeting Room. I thought the duct clearance was established by the largest duct on the floor, but I guess I'm confused what happens at the higher ceiling'd spaces. Do you use the clearance for the 2nd floor? or just the largest duct in the higher space?
You do not have the required permissions to view the files attached to this post.
te_mcg
 
Posts: 3
Joined: Sat May 23, 2015 3:43 pm


Return to CDS - CONSTRUCTION DOCUMENTS & SERVICES

Who is online

Users browsing this forum: No registered users and 57 guests

cron